|

Two International Finance Centre, Hong Kong, China

Statistics
| Name: |
Two International Finance Centre |
| Location: |
Hong Kong, China |
| Floors: |
88 |
| Antenna: |
- |
| Spire: |
- |
| Roof: |
415 m |
In-Depth Analysis by Michael W.
Su
At the
moment of this writing, Two International Finance Center stands as the tallest
building in Hong Kong. This slender, graceful tower was designed by Cesar Pelli
& Associates in collaboration with Rocco Design Limited and engineered by Ove
Arup & Partners to reach 416m at the top of its distinctive crown of curved
spikes, 407m at its covered roof, and 402m at the highest habitable floor. In
Hong Kong, extreme lateral loads due to typhoons and earthquakes are a
particular consideration. As such, designers for this locale often find
themselves delicately balancing structural requirements and usable floor plates
in order to achieve necessary structural stiffnesses without yielding too much
area to services or columns. For 2 IFC, in particular, the designers opted for
the combination of a massive reinforced concrete core of square cross section
with eight rectangular composite “mega-columns” of steel and concrete and eight
much smaller steel columns. Like the Jin Mao Tower completed five years earlier,
this ensemble of structural elements is arranged into a cruciform configuration
with mega-columns in line with the core to counter major gravity and lateral
loads and small corner columns to resist minor gravity loads from the
extremities of the floor plate. Specifically, the high strength steel and
concrete, combination of three 3-story tall core-embedded (called “retro-cast”)
outrigger trusses and belt trusses, exceptionally lightweight curtain wall
system, and wide spacing (24m) between the mega-columns on each façade all
combine to provide sufficient gravity, lateral, and torsional resistance so as
to render interior or more-substantial corner columns unnecessary.
From the foundation to the sixth floor above grade, the mega-columns are formed
from six 90mm thick high strength steel sections enclosed with high strength
concrete. With rising height, the number of steel sections is reduced from six
to three to two and, finally, to one on the upper floors as the size of the
column and the strength of concrete is also diminished. These changes in the
steel-to-concrete ratio are accompanied by a change in the coupling between
steel and concrete such that from the foundation to the 26th floor,
the mega-columns are essentially reinforced concrete columns, while beyond the
26th floor, the mega-columns effectively act as steel columns with
concrete cladding and fireproofing. The result is a structure that testifies to
the advances in engineering and material science achieved in just the few years
since the Jin Mao Tower was completed. In fact, among myriad other
accomplishments, the contractors for 2 IFC set records when they poured concrete
for the world’s largest “cofferdam”, erected the world’s largest outrigger, and
pumped concrete over 28m higher than the previous record holder – the Petronas
Towers’ record-setting 380m.
Besides the remarkable simplicity of its structural system – and the resulting
expanse of column-free spaces, 2 IFC was also erected in record time. Due to the
relative accessibility of bedrock at the site, a highly unusual – and
record-setting – circular “cofferdam” 61.5m in diameter with 1.5m thick walls
and averaging 40m deep extends from grade to bedrock. The tower’s 6.5m thick
concrete raft foundation is poured directly atop this exposed bedrock. Then, a
sufficient quantity of basement slabs is formed solely to facilitate the
erection of the tower. This simultaneous bottom-up and top-down approach
permitted construction to begin on the core and column structure of the tower
well before the completion of the basement, as much as 18 months. Also, each
mega-column is formed by its own hydraulic, self-climbing steel formwork. The
reinforced concrete core with an approximately 3x3 internal column grid is also
raised with its own formwork. Finally, flooring and façade systems were designed
with minimum number of components by relying on long, deep perimeter girders and
simply connected beams for the floors. In turn, floorslabs are formed from
concrete poured on steel decks on these simple beams so that the pours did not
even require temporary supports before fully curing. As a result of these
time-saving innovations, the contractors were able to attain the elusive goal of
raising one floor every three days even as they simultaneously worked on other
sections of the tower.
|